IFM-ACGreen CarbonTier 2 — standardmedium confidence

Improved Forest Management / Avoided Conversion

Forest management practices that reduce emissions (e.g. sustainable harvest) or prevent conversion of forested land.

reduced-impact loggingextended rotationavoided conversion
Measurement tier
Tier 2 — standard
Model confidence
medium
Uncertainty deduction
−15% on net credits

About this methodology

The Improved Forest Management / Avoided Conversion profile (IFM-AC) is a Green Carbon methodology profile used by the Athlas Verity engine to estimate and independently verify carbon outcomes for reduced-impact logging, extended rotation, avoided conversion. Forest management practices that reduce emissions (e.g. sustainable harvest) or prevent conversion of forested land.

Athlas classifies this profile at Tier 2 — standard with medium confidence. Estimates are derived from directly observable satellite signals, and a conservative uncertainty deduction of 15% is applied to net creditable volume. The profile sets parameterisation, dataset bundles and evidence requirements; the core accounting chain is shared across the platform.

Verification is evidence-led. A project mapped to this profile must supply 4 mandatory evidence items plus 1 optional supporting record. Athlas cross-checks the submitted project boundary and documents against 3 Earth-observation and ancillary data layers, then issues a tamper-evident verification report that can be reviewed independently.

How Athlas verifies this

  1. 1

    1. Boundary & evidence intake

    The project boundary (GeoJSON) is ingested and validated against the 5 evidence requirements defined for profile IFM-AC. Ownership, legality and truthfulness declarations are recorded for the audit trail.

  2. 2

    2. Baseline reconstruction

    Historical reference conditions are reconstructed from the UMD/hansen/global_forest_change_2023_v1_11 layer (treecover2000) using a mean reducer at 30 m, giving a defensible counterfactual for reduced-impact logging.

  3. 3

    3. Satellite measurement

    The primary signal is measured from UMD/hansen/global_forest_change_2023_v1_11 (bands treecover2000) with a mean reducer at 30 m, combined with the remaining 2 supporting layers for terrain, moisture, climate and land-cover context.

  4. 4

    4. Conservative accounting

    Results are passed through the shared accounting chain using the profile's own parameters, then reduced by the profile uncertainty deduction of 15% to give a conservative, uncertainty-aware creditable volume.

  5. 5

    5. Report & on-chain anchoring

    A verification report is generated with a tamper-evident hash and anchored immutably, so the Green Carbon result for IFM-AC can be independently reviewed and its retirement tracked.

Satellite & Earth-observation layers

RoleDatasetBandsReducerScale
forest cover baselineUMD/hansen/global_forest_change_2023_v1_11treecover2000mean30 m
vegetation indexCOPERNICUS/S2_SR_HARMONIZEDB8, B4median10 m
disturbance indexLANDSAT/LC08/C02/T1_L2SR_B5, SR_B7median30 m

Profile parameters

carbonFraction
0.47
deadwoodToAgbRatio
0.11
litterToAgbRatio
0.01
harvestReductionPercent
0.25
bufferRiskPercent
0.15

Required evidence

  • Project boundary (GeoJSON)

    Required · accepts geojson, json, zip

  • Management plan

    Required · accepts pdf

  • Permits, legality & land status

    Required · accepts pdf, jpg, png

  • Baseline / reference study

    Optional · accepts pdf

  • Data truthfulness declaration

    Required · accepts pdf, jpg, png

Verification workflow

Frequently asked questions

What is the Improved Forest Management / Avoided Conversion (IFM-AC) methodology profile?

It is a Green Carbon methodology profile in the Athlas Verity library. Forest management practices that reduce emissions (e.g. sustainable harvest) or prevent conversion of forested land. It applies to reduced-impact logging, extended rotation, avoided conversion and sets the parameters, satellite dataset bundle and evidence requirements used to verify a project mapped to it.

What evidence is required for profile IFM-AC?

Mandatory evidence includes: Project boundary (GeoJSON); Management plan; Permits, legality & land status; Data truthfulness declaration. Optional supporting records such as Baseline / reference study strengthen the assessment.

How does Athlas verify a IFM-AC project with satellites?

Athlas measures the project using 3 Earth-observation layers, including UMD/hansen/global_forest_change_2023_v1_11 (treecover2000). Estimates are conservative: a 15% deduction is applied to net credits.

Which verification domain does IFM-AC belong to?

Profile IFM-AC belongs to the Green Carbon domain. Projects are routed through the corresponding verification workflow and dashboard at the Green Carbon verification area.